The power maintenance is now complete
There is change to the original plan for the critical power installation works being carried out by KUSCO with brief outages to power affecting network, wireless and IT equipment:
Roehampton Vale Campus will now take place Thursday July 29 - 6am to 9 am
Due to critical power installation works being carried out by KUSCO there will be brief outages to power affecting network, wireless and IT equipment in the following areas:
Tuesday July 27 - 6am to 8pm
Roehampton Vale Campus
Tuesday July 27 - PM - 2 Hour Outage
River House
Wednesday July 28 - AM - 2 Hour Outage
Penrhyn Road Reg Bailey
Wednesday July 28 - PM - 2 Hour Outage
75 Penrhyn Road Halls
Thursday July 29 - AM - 2 Hour Outage
Kingston Hill Campus Coombehurst Court
Thursday July 29 - AM - 2 Hour Outage
Tolworth Court Sports Ground